ABB wins power contract in Brazil

5 May 2007


The company will deliver four substations for Companhia de Transmissão de Energia Elétrica Paulista (CTEEP), the power transmission company in Sao Paulo. The work is scheduled for completion within about 14 months with the equipment installed in the cities of Ribeirão Preto, Sumaré, Santa Cabeça and Capivara. ABB will also oversee the civil works, installation and commissioning of the system.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.