The government of the Republic of Altay and the administration of the Altay Territory have agreed to relaunch a project for the construction of a hydropower plant on the Katun river. The project was shelved during the collapse of the Soviet Union, and following environmental protests.

The two regions are to set up a joint-stock company called the Energy of Altay Rivers Corp which will draft design documentation and carry out a feasibility study for the hydro scheme. The plant will be located in the Altay mountains, 130km from Gorno-Altaysk. Total cost of the scheme is put at around $1 billion.

The region currently has insufficient capacity to supply local demand. The Republic of Altay receives all its power from Altay Territory; the latter imports 70 per cent of its electricity from neighbouring Siberia.

Under the newly proposed plans, the project will have a 50m dam, only one third of the height of the original proposal.

The Republic of Altay would consume around 15 per cent of the power generated. The remainder would be exported. Current levels of supply in the region are one quarter of that in most of Russia.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.