Australian blackout threat as Basslink hit by bad weather

24 February 2005


Six of eight 200 tonne transformers heading for Australia’s Basslink transmission project have been damaged after a ship lost its rudder in the Great Australian Bight and was subsequently struck by rough weather. As a result, the A$780 million (€464 million) Basslink project that is to allow a 600 MW power transfer between Tasmania and Gippsland in mainland Australia will be delayed by as much as five months until April 2006.

The transformers were being transported from a Siemens plant in Germany when the accident happened. Siemens project director Guenther Wanninger has reportedly said that the six A$2 million (€1.2 million) transformers would be rebuilt from scratch in Germany. They should be on site by December.

The delay may see both Victoria and South Australia facing blackouts as peak demand rises during the summer, shaving already strained capacity margins razor thin.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.