Basemat at Summer 3 nuclear plant completed

8 November 2013


South Carolina Electric & Gas Company has announced that the concrete basemat for unit 3 of the VC Summer AP1000 nuclear power plant was completed on 4 November. This milestone comes just seven months after first concrete pouring for VC Summer 2, and brings the number of nuclear reactors under construction in the United States to five.

The 6-foot thick concrete basemat provides a foundation for the containment and auxiliary buildings that are within the nuclear island. Around 7000 cubic yards of concrete was needed for the concrete pour, which covered an area of 32,000 square feet. Nearly 500 people worked for over 43 hours on the weekend of the 2-3 November, according to Jeff Benjamin, nuclear power plants senior vice president at Westinghouse.

Westinghouse and its consortium partner Chicago Bridge & Iron Company (formerly Shaw Group) were awarded an engineering and procurement contract for the two units in 2008. "Thanks to the lessons we learned from the Unit 2 concrete pour and also from our other construction projects, we were able to complete this milestone safely and even more efficiently," Benjamin said. The concrete pour for VC Summer 2, completed on 11 March 2013 took a total of 51.5 hours.

Benjamin also said that there has been "significant progress" on Summer 2. "Some of the progress includes the placement of the containment vessel bottom head and placement of the reactor vessel support module, as well as concrete placement that will enable further progress on the nuclear island," Benjamin said. One of the cooling towers is almost complete, and work continues on major modules, the containment vessel and auxiliary building.

SCE&G and Santee Cooper are planning two 1117 MW Westinghouse AP1000 reactors at the existing VC Summer site in South Carolina. Summer 2 is currently scheduled to be complete in "late 2017 or early 2018," according to SCE&G. It will be followed by Summer 3.
Once the units begin operation SCE&G anticipates its generation mix will be about 30% nuclear, 30% natural gas, and 30% scrubbed coal, with the balance in hydro, solar and biomass.

 



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.