Centrica plans new UK CCGT station

19 June 2006


The £400 million ($741 million) development, which includes a link to the national gas transmission network and the original acquisition cost, is due to begin commercial operations during winter 2008/2009.

Centrica has awarded Alstom a fixed price engineering, procurement and construction (EPC) contract to develop the combined cycle gas turbine plant.

Alstom will also provide maintenance support to Langage for an initial 12 year period under a long term service agreement.

Sir Roy Gardner, chief executive of Centrica, said: “Faced with a volatile wholesale energy market and a predicted reduction of power generation sources in the UK over the coming years, this major investment signals Centrica’s commitment to secure the future energy needs for our British Gas customers.”

Langage’s location in the south-west, which has little existing power generation capacity, means Centrica will benefit by receiving Transmission Network Use of System (TNUoS) payments. Centrica’s investment has also helped to underpin National Grid’s reinforcement to the gas and power networks in the region.


Related Articles
CCGT and wind to dominate UK energy growth



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.