Commissioning of second Ling Ao II unit gets underway

2 June 2010


Unit 2 of Ling Ao phase II (Ling Dong 2) nuclear power plant has begun commissioning after completing a six-day 48 minute cold function test.

The plant's other reactor Unit 1 finished its cold test on 25 September. It has just celebrated the start of core loading operations.

Both reactors are 1000MWe CPR-1000 units. Unit 2 is predicted to start commercial operation in June 2011.

According to CGNPC, unit 2 had a transformer fire on May 16, though on-site fire suppression systems put it out without casualties or any effect on plant systems.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.