Dabhol restart expected late 2006

23 June 2005


Indian gas company Gail is expected to register a new company within the next few days that will take over the group’s role in the mothballed Dabhol plant in Maharashtra. Comments attributed to Gail Chairman Prashanto Banerjee indicate that the plant will begin operations in the second half of 2006.

The $2.9 billion Dabhol project is expected to produce some 2,184 MW when completed having been delayed over a contractual issue with sole customer the Maharashtra state electricity board.

Initially, Gail and power utility the NTPC would form a 50:50 joint venture holding Dabhol before the Maharashtra State Electricity Board would move to eventually hold 15% equity. GAIL, NTPC and Indian financial institutions would subsequently hold 28.3% each.

Banerjee reportedly said. "What we are doing now is an independent exercise. After the settlement is done, the assets could be acquired by bidding or by a negotiated transfer. It would be an asset transfer with no liability."




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.