Delayed restart cuts BE's income

17 July 2003


Under the terms of the February sale of its 82.4 per cent interest in Bruce Power, BE was to receive an additional $36 million if Bruce 4 started by 15 June, and another $36 million if Bruce 3 began operating by 1 August. Any delay in the restart of each unit results in the payments being reduced by 10 per cent per month, falling to zero after nine months. Bruce Power is to pay the provincial government of Ontario any amounts forfeited by BE.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.