Doosan orders Vinh Tan 4 STGs

23 July 2014


Doosan Heavy Industries and Construction of Korea and Mitsubishi Corporation of Japan have placed an order with Toshiba for two 600 MW supercritical steam turbine generators (STGs) for the Vinh Tan 4 thermal power plant in Vietnam.

Doosan and Mitsubishi are members of the consortium carrying out the engineering, procurement and construction (EPC) of the plant, which is located in Binh Thuan province.

Toshiba will start delivery of the equipment in 2015 and the 1200 MW plant is scheduled to start operating in 2017.

The EPC partners started construction of the plant in March 2014. The project is part of Vietnam's plans to expand power generating capacity from 26 836 MW in 2012 to 75 000 MW in 2020, and to 146 800 MW by 2030.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.