Endesa brings Aitona mini-hydro plant on-line

11 November 2005


The plant has installed capacity of 4.9 MW and uses water discharged into the Segre river from the Seròs II hydro plant, also owned by Endesa, along the final stretch of the Catarralà ravine. The plant is included in the Seròs hidro complex that in the past was the origin of Utxesa reservoir.

The plant comprises two identical 2.45 MW semi-Kaplan turbines which permit a flow of up to 60 m3 per second each, with a drop of 4.72 m.

Average production capacity is estimated at an annual 14.3 GWh

Total investment in this new mini hydro plant amounts to around €6.5 million.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.