Endesa earmarks Canaries investment

15 March 2007


As part of the expansion plans, 210 km of high voltage lines and 240 km of medium voltage lines are being built as well as seven substations on the islands.

In 2006 Endesa invested €268 million in the Canary Islands to meet rising demand, boosting capacity by 12%.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.