Endesa’s plant upgrade

17 August 2006


Parts of the boiler and the turbine at the As Pontes plant will be replaced, extending its life by 25 years. The facility is scheduled to come on stream at the end of 2007.

Duro Felguera will be responsible for the work on the boiler, Alstom, will work on the precipitator and Graver will convert the ash system.

The first 369 MW unit was converted in the first half of 2005, similar improvements in the two remaining generating units are planned each year until 2008.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.