European outage blamed on human error

30 November 2006


According to the latest findings of the company’s in-house investigation into the causes for the disruption, “human error, as opposed to any technical malfunctions, was chiefly responsible.”

The results of a detailed reconstruct of the chain of events that led to the disruption reveal that “an E.On control centre had assessed developments correctly… but, owing to time pressure, had not made use of all technical options for a comprehensive situation analysis.” The centre had not checked whether the outage of an additional transmission line might overload the power grid when assessing the risks associated with switching off a power lines to allow a ship’s passage along the River Ems. About half an hour later, another high voltage transmission line was overloaded – for reasons that are not yet known. To compensate for this, a number of lines were switched together at a substation and, contrary to the assessment of the control centre staff, this did not decrease but further increased the load on the power grid, which, in turn, triggered an automatic shutdown procedure.

The preliminary results of the UCTE investigation into the incident are due to be released in the next few days.


Related Articles
Power cuts hit Western Europe



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.