The Estlink connection between the 330 kV substation at Harku in Estonia and the 400 kV substation at Espoo in Finland is one of the priority projects in a European Union plan to improve cross-border power infrastructure, reduce blackouts and help create more efficient power markets in Europe. An estimated 2 TWh of electricity will be delivered anually into the Nordic electricity market from Baltic generation.

The partners in the Estlink project are the three Baltic power utilities - Eesti Energia, Latvenergo, Lietuvos Energija - as well as Pohjolan Voima and Helsinkin Energia of Finland.

The 105 km underground and underwater HVDC link was designed, built and installed by ABB using its HVDC Light technology in a record 19 months using modular construction.

The project, which was announced in late April 2005, is worth $110 million for ABB.


Related Articles
ABB unveils next generation HVDC
ABB opens HVDC test facility



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.