A € 200 million project to link the grids of Finland and Sweden with a second submarine cable has been agreed. The 600-800 MW sea cable between the two Nordic countries will be in use in 2010 with full capacity available from 2011. The new cable, planned by Fingrid and Sweden's state-owned Svenska Kraftnat aims to remove remaining bottlenecks and enhance coordination between the region's transmission system operators.

An existing 550 MW submarine cable is being repaired with work expected to be finished in early March.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.