Fukushima units have been air-sealed

9 November 2011


Operator Tepco has carried out an operation to seal the stairwells, hatches and other penetrationsthat lead to the Fukushima Daiichi units 1-4 turbine halls and other buildings to reduce the spread of radioactive dust.

The dust is carried by draughts created by the movement of water from the building basements as they are pumped dry. The work, carried out in October, involved fitting non-combustible plastic sheets over the openings and sealing with tape or urethane foam. Some entryways were blocked with boards to prevent access through the barrier. In the units 2,3 and 4 turbine buildings, the large equipment hatch was sealed with balloons.

•Tepoc reported on 8 November that the presence of the short-half life fission product Xe-135 detected a week before did not indicate a dangerous situation. It was detected in small quantities, the detected quantity did not change after injection with boric acid, and because no other reactor parameters changed. It said that the fission product reflected a continuous low-level fission reaction, and was only detected because of a new, sensitive measuring method. In a separate statement, the Japanese nuclear regulator NISA concurred with these conclusions.

•Japanese national broadcaster NHK reported that the Japanese environmental registry has begun a detailed survey of radiation levels in air within the 20km exclusion zone around the plant, in order to determine decontamination priorities when work starts in January. It will use unmanned helicopters and cars to carry out the survey at 100m intervals. The NHK report was published by Japan Atomic Industrial Forum's Atoms in Japan information service.

•JAIF reports that Japan's advisory committee on the Fukushima cleanup has released a provisional estimate that cleanup of the station will take 30 years or more. Work to remove fuel from spent fuel ponds could begin as early as 2014. After damaged primary containment vessels are repaired and filled with water, melted fuel could begin to be removed from them in about 2021. The committee chairman, Kyoto professor Hajimu Yamana, said that definitive estimates require investigation of the interior of the reactors.

Regular updates may be found on the website of our sister journal, Nuclear Engineering International, reachable on <www.neimagazine.com> or by clicking on the link in the navigation bar to the left of this page.

The following sites are also posting continuing updates:

<http://www.tepco.co.jp/en/index-e.html>

<http://www.iaea.org/>

<http://www.jaif.or.jp/english/>

<http://bravenewclimate.com/2011/03/15/tepco-reactor-status/>

<http://www.world-nuclear-news.org/>

<http://www.kantei.go.jp/foreign/index-e.html>




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.