GE first for LMS100

11 July 2006


The turbine can go to full power from a cold metal start within 10 minutes and will be operated as a peaking plant.

Plant construction began in August 2005 with delivery of the gas turbine generator set in November 2005. First fire was achieved in April 2006 with full-load operation in May.

The aeroderivative gas turbine delivers 100 MW with thermal efficiency of 44-50%.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.