Hub coal plant on track

16 October 2018


Construction of a 1320 MW coal fired power plant in Hub, Pakistan is on track for commercial operation, according to the developers.

China Power Hub Generation Company (CPHGC) says that the project reached a major milestone in September when it interconnected with the national grid network in Pakistan.

“The achievement of this major milestone … indicates that we are on track to meet the deadline of August 2019 for the commercial operation date,” said Zhao Yonggang, CEO of CPHGC.

According to CPHGC, the Hub plant achieved back energization of its 500 kV gas insulated substation from the Jamshoro side of the transmission lines. After energization, the plant achieved energization of the start-up transformer and 10 kV auxiliary power system in preparation for system commissioning of Unit 1.

CPHGC is a joint venture between China Power International Holdings and Pakistan’s Hubco created to build the $2 billion, 2 x 660 MW power plant in Balochistan province.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.