Innogy ahead of schedule

5 February 2002


Innogy has completed the 100 MW Evander Andrews power complex for Idaho Power two weeks ahead of what was already seen by the company as a very tight schedule. The EPC contract provided power in 16 weeks. The new gas fired plant uses two westinghouse simple cycle gas turbines each of 50 MW.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.