Ling-Ao 1 goes critical

28 March 2002


China's fifth nuclear reactor, the 984 MWe Ling Ao unit 1, achieved core criticality on February 4th three weeks ahead of schedule. The project is owned by Ling Ao Nuclear Power Company. Framatome, who supplied two similar units on the nearby Daya Bay site, provided the two nuclear islands, along with erection and supports services. The first fuel loading of the plant was completed on December 14 last year.

LANPC will now begin physical tests to verify core compliance, following which power will be increased in the reactor in stages. These operations will be carried out under the supervision of the Chinese National Nuclear Safety Administration (NNSA). The unit was scheduled for connection to the grid at 10 per cent power in March, while commercial operation is scheduled for June 2002.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.