Alstom has won the contract to retrofit the low-pressure steam turbines together with a new generator at Unit 1. The company will supply eight low-pressure steam turbine inner blocks.

Designed to enable high availability with long service cycles, the efficiency of the power plant will be increased by about 1% as a result of the project, increasing electrical output of both units by about 25 MW.

Alstom’s Swedish subsidiary is responsible for the contract, which includes - in addition to the retrofit of the low-pressure turbines - the new generator for Unit 1, the corresponding generator for Unit 2 ordered earlier, and all required design and installation. The value of the contract totals about €100 million.

The installation will be carried out during the 2010 and 2011 annual service outages.

The announcement follows a short shutdown of Unit 2 at the plant as a result of a fire on a turbine bearing. The fire was caused by the heating of oily insulation material on the turbine. The oily insulation material has now been replaced with clean insulation.


Related Articles
New generator for Olkiluoto 2
TVO begins EIA



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.