Nuon launches offshore project

9 May 2006


The construction materials for the € 200 million project will be brought to IJmuiden harbour, from where they will be shipped out by the Svanen, Ballast Nedam’s floating crane.

Once the foundations have been placed installation of the Vestas wind turbines will begin during the summer with completion scheduled for the autumn. Operations for the farm, a project of the NoordzeeWind joint venture between Shell and Nuon, are due late 2007.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.