Power projects cancelled

5 September 2002


Rapids Power has announced cancellation of plans to build a 225 MW combined heat and power plant, in Grand Rapids, Minnesota, which was to serve a paper mill as well as supplying power to the grid. The announcement follows a decision last spring to delay seeking a Certificate of Need permit.

The company said that the cost of the plant was too high to support marketable electricity. A downturn in the US electricity market and higher-than-expected construction costs are said to be behind the decision, as well as the weakness of the paper industry.

In North Carolina, meanwhile, Duke Energy has halted construction of a 570 MW power plant near Deming and postponed the start of work on a second plant near Clovis. Once again the slump in the price for wholesale power is cited as the reason for moves. A new construction schedule for the $250 m Deming plant is expected to be announced, but the fate of the Clovis project is not known.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.