Sener consortium completes Empalme I CC plant

2 May 2019


Mexico’s Federal Electricity Commission (CFE) and the Sener-OHL have signed the Provisional Acceptance Report for the Empalme I combined cycle plant.

The 770 MW power plant is one of the most efficient in CFE’s portfolio and was built by the Sener-OHL consortium under a turnkey engineering, procurement and construction (EPC) contract signed in 2015.

The plant is equipped with two gas turbines, two heat recovery steam generators and a single steam turbine. Sener-OHL was also responsible for building a cooling water intake facility for the Empalme I and II plants under the $477 million contract.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.