Siemens gas turbine package to Minnesota

2 July 2007


The Elk River plant is unique because of the fast-start capability of the gas turbine, which permits the Elk River plant to deliver approximately 150 MW of power to the grid within 10 minutes.

With a nominal capacity of approximately 200 MW, the plant is expected to be commissioned in May 2009. The Siemens scope of supply encompasses the SGT6-PAC-5000F gas turbine, an air-cooled generator, the exhaust stack and the plant control system. The order volume is $41 million.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.