Sri Lanka

5 October 2002


Under a E13.6 million contract from the Ceylon Electricity Board (CEB), VA Tech T&D will deliver, erect, install and commission two substations which when completed will form part of the Kukule Ganga hydroelectric power project. The substations will be located in Kukule and Matugama in southern Sri Lanka. The scope of delivery for the turnkey 145 kV air-insulated switchgear also includes transformers, circuit breakers, current transformers and voltage transformers, as well as the protection, control and communications equipment.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.