Tepco: it will take three years to resolve mid-term Fukushima issues

24 July 2011


As small-scale site remediation works such as patching the unit 3 turbine hall roof continue, electrical utility Tepco has published an update of its progress in achieving short- and medium term goals in stabilising the damaged Fukushima Daiichi site.

It has concluded that to achieve continuous cold shutdown of all reactors on the site, installation of a full-fledged water processing system, establishment of a groundwater contamination shielding wall, building a temporary cover for units 3&4, and mitigation of ocean contamination, among other necessary tasks, could take in all three years.

TepcoPhas reported that it has met all of the requirements of its first step, in that site radiation has fallen steadily, that reactors and spent fuel pools have stable cooling, and that treatment operations have begun of accumulated contaminated water. It has calculated provisionally that a worker on site would be exposed to 1.7 mSv/year (compared with the regulatory limit of 1 mSv/year). It said that if one assumes that all radiation detected is from current emissions, the release rate is about 1 billion Bq/hr; this is two millionths of the emission rate immediately after the accident.

Tepco's step two stabilisation goals, expected to last from three to six months, include installing alternate spent fuel cooling systems at unit 1 and unit 4, installation and commissioning of two types of desalination systems (based on distillation and reverse osmosis), construction of a centralised monitoring system in the main anti-earthquake building, continuing pipe sheet pile drilling to permanently isolate the unit's intake bay from the sea, removing debris, evaluating the seismic resistance of reactor buildings and improvement of worker health monitoring, and consideration of a so-called 'full-fledged' water treatment system, along with other work.

After noticing a drop in flow rate, Tepco has begun work to flush the air out of the lines and into tanks. Connecting pipes with bellows have been replaced with smooth-walled pressure-resistant hoses, and ventilation lines have been added to the first treated water tank.

Regular updates may be found on the website of our sister journal, Nuclear Engineering International, reachable on <www.neimagazine.com> or by clicking on the link in the navigation bar to the left of this page.

The following sites are also posting continuing updates:

<http://www.tepco.co.jp/en/index-e.html>

<http://www.iaea.org/>

<http://www.jaif.or.jp/english/>

<http://bravenewclimate.com/2011/03/15/tepco-reactor-status/>

<http://www.world-nuclear-news.org/>

<http://www.kantei.go.jp/foreign/index-e.html>




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.