UES forecast equipment demand list published

27 February 2007


The total investment programmes will reach RUB3.1 trillion ($119 billion) with UES companies spending over RUB1.8 trillion ($69 billion) on new power projects and with as much as RUB1.3 trillion ($50 billion) going on grid infrastructure development.

The investment programme envisages construction of combined-cycle power plants, requiring over 100 gas turbines, 67 steam turbines, and 125 waste heat recovery boilers. Over 70 steam turbines are needed for the large-scale construction of coal-fired power units with circulating fluidized bed combustion, VIR-technology, and ultra-supercritical boilers. Furthermore, the energy industry will need over 150 transformers with a combined capacity of 50,000 MVA to be installed at the power plants, 260 turbine generators with the capacity of 45,000 MW, and 48 boiler plants with 45 t/h steam generating capacity.

In addition, the UES hydro arm, HydroWGC, will need 45 hydroturbines with a combined capacity of 5,000 MW, 43 generators, and 18 transformers with a capacity of 3,500 MW. A further 25 hydro turbines with the combined capacity of 252 MW and 25 generators are needed to modernize the small-scale hydro plants.

By 2011, collectively UES intends to build 34,200 MW of new generating capacity with over RUB630 billion ($24 billion) spent on principal thermal power equipment such generators and turbines. Procurement of high-voltage equipment and materials for bulk transmission grids will make about RUB200 billion ($7.6 billion) by 2011, UES said.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.