Voith Siemens wins Swiss contract

5 March 2007


The deal covers replacement of the electromechanical equipment at the plant, including delivery of seven 6.7 MW Kaplan turbines, together with generators and governors as well as the complete control package. The new Kaplan units will replace seven Francis turbines which began operations as early as 1915, the new equipment will be in place by 2012.

Uprating the turbines increases the flow rate from 385 m³/s to 500 m³/s and is expected to improve performance by about a third from 246 GWh to 314.5 GWh annually.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.