Germany is ‘not hydrogen ready’

15 November 2022


Germany is not sufficiently prepared for the ramp-up of the hydrogen economy. This is the conclusion of the ‘H2-Bilanz’ (H2 balance), an analysis by E.ON based on data from the Energy Economics Institute at the University of Cologne. Looking ahead to 2030, it appears that neither the domestic generation capacity of green hydrogen is sufficient nor can the German import demand be met. In addition, there is a lack of infrastructure to bring hydrogen to customers.

E.ON intends to publish the H2-Bilanz at regular intervals. Its goal to show the current status quo of hydrogen ramp-up in Germany. The analysis includes specific project plans up to 2030 and beyond. Examples for indicators are green hydrogen generation capacity, import volumes, infrastructure and costs. It is this analysis of the current data shows that Germany is not hydrogen-ready.

Taking into account all projects planned to build-up electrolysis capacity, generation capacity will be 5.6 GW by 2030. This is only slightly more than half of the national generation capacity that the German government says should be achieved by 2030. If the development of national hydrogen production does not proceed more quickly, the existing import demand will increase even further. Here, too, the H2-Bilanz shows a large gap: Based on the German Energy Agency's lead study, which assumes a hydrogen demand of 66 TWh by 2030, the import gap is currently 50.5 TWh hours. This is approximately equivalent to the monthly natural gas consumption in Germany for September 2022.

Furthermore, there is no infrastructure to transport hydrogen from the state's borders – in particular from ports − to the customers who depend on it for their transition to green technologies. There are currently only 417 km of hydrogen network − less than 0.1 % of Germany's gas network.

E.ON points out that there is still no definition of green hydrogen at EU level. This inhibits investment decisions because plant operators do not know whether their current plans will meet the criteria.

Uncertainty is also slowing down the development of a hydrogen network. The EU Commission's proposal for unbundling would not allow natural gas and hydrogen networks to be managed within one company in the long term. This would mean that gas network operators would lack the incentive to convert their networks to H2.

Also, the support environment in Germany is not yet mature enough for a completely new industry to emerge by 2030. The market ramp-up requires a pragmatic funding framework for investments in hydrogen projects. Support for operating costs is needed to encourage companies to switch to green alternatives.?

Approval processes for hydrogen production and import need to be significantly accelerated. The legal classification ‘of overriding public interest’ that is planned for wind energy and photovoltaics must also apply to hydrogen projects. For the construction of new hydrogen pipelines, this regulation has already been included in the current legislation, but only temporarily until the end of 2025. However, the major investment phase will probably not occur until after that.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.