Olkiluoto 3 fuel loading in 2012

11 June 2010


Fuel loading at the Olkiluoto 3 EPR in Finland is now expected at the end of 2012, about four years later than envisaged in the original schedule.

The new date was given in a proposal submitted on 4 June by the Areva-Siemens consortium supplying the plant to its Finnish customer, TVO, outlining a timetable and milestones for completion of the project, up to fuel loading.

The main civil works are completed and almost all the buildings are now fully closed and weatherproofed. There were initial delays in carrying out pipework installation, but this is now fully underway, with installation of major primary circuit components, such as the reactor pressure vessel, expected shortly.

In addition, the regulator has now accepted the instrumentation and control system architecture for the plant, allowing preparations for plant commissioning to begin.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.