Rosenergoatom and Sevmash begin floating nuclear plant construction

18 April 2007


The base section of the plant, Academic Lomonosov, has been officially laid at the Sevmash yards in Severodvinsk.

Sergey Obozov and Vladimir Pastukhov, the heads of Rosenergoatom and Sevmash respectively, have signed a declaration of intent to build a series of floating nuclear plants from 2008–2016 with construction time falling to three years from four by the third unit. Kiriyenko added that this could be reduced further to 2 - 2.5 years.

Rosenergoatom is also planning to increase the rector capacity from the units currently based on 70 MW ice-breaker KLT40C reactors to medium-capacity plants based on nuclear submarines with a capacity of 300–400 MW. The first plant’s reactors have been designed by I.I. Afrikantov Experimental Design Bureau of Machine Building.

The Academic Lomonosov, to be developed at a cost of $200 million, is to be launched in 2010 with most of the electricity produced supplied to Sevmash, and just 20% sold.

The concern is considering six possible sites in the power starved Northeastern region for additional units, including the Kamchatka, Chukotka, Jakutia and Krasnoyarsk regions.

By 2015 Rosenergoatom plans to create a fleet of seven floating plants.


Related Articles
Floating nuclear power station underway
Sevmash floating nuclear plant contracts



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.