RTE announces capacity market results

18 March 2020


French transmission operator RTE has announced the winners of 7-year capacity market (CM) contracts following a call for tenders held in 2019.

RTE has awarded contracts to 377 MW of capacity, including 253 MW of battery projects and 124 MW of remand response.

The contracts are worth €28k/MW/year or €29k/MW/year, depending on the delivery window, RTE said on its website.

The CM tender is part of France’s PPE long-term energy programme and was designed to procure low-carbon, flexible capacities to improve security of supply in France. Projects will deliver in either 2021 or 2022, RTE said.

The results of the tender show that three firms – Total Flex, Amarenco and RES – will share 90 per cent of the battery contracts awarded, where only nine developers in total secured contracts. Some 60 per cent of offers in the tender were from demand side response capacity, while 40 per cent came from batteries.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.