Sungrow will supply battery storage and power conversion equipment for the 150 MW / 300 MWh Hazelwood Battery Energy Storage System expansion (HBESS 2) in Victoria, Australia, working with project partners ENGIE and Elecnor. Commercial operation is targeted for 2028.
Sungrow Australia will act as technology provider, while Elecnor will serve as balance-of-plant (BOP) contractor. The installation will use 66 ST5015-UX battery storage units from Sungrow’s PowerTitan 2.0 range, together with 33 SC6900UD-MV power conversion system (PCS) inverters and the company’s EMS3000 energy management system.
The two-hour battery system is intended to store electricity and discharge it when required, helping balance supply and demand in Victoria and the wider National Electricity Market (NEM) as renewable generation increases.
The project will also incorporate grid-forming technology. This can enable battery inverters to contribute to voltage and frequency control and respond rapidly to changing grid conditions, supporting power system operation as the share of variable renewable generation grows.
Sungrow says its PowerTitan 2.0 system uses liquid cooling and integrated battery management to support temperature control, safety monitoring and operational performance. The PCS equipment is designed to convert power between the battery’s direct-current system and the alternating-current grid.
Thomas Hou, managing director of Sungrow Australia, said the project represented a step forward for grid-forming energy storage in Australia and would support grid stability and renewable energy integration.
The expansion adds to the development of utility-scale battery storage in Victoria, where such systems can provide flexible capacity alongside renewable generation and existing power infrastructure.