CPUC approves renewables transmission links

12 April 2007


When complete, the 11 phase Tehachapi project will include a series of high-voltage transmission lines capable of delivering 4,500 MW.

Segments 2 and 3 include five components: a new 34 km, 500 kV line connecting SCE’s existing Antelope and Vincent substations, two new substations to be named Windhub and Highwind, located near Mojave and Monolith, a new 41 km, 500 kV transmission line connecting SCE’s existing Antelope Substation with the proposed Windhub Substation, and a new, 16 km, 220 kV transmission line connecting the Windhub and Highwind substation.

The new lines are expected to be operational in early 2009.

The first segment was approved by the CPUC in March and SCE will file an application next June to build the remaining segments.

The Tehachapi project is part of SCE’s five-year, $4.3 billion transmission expansion programme.


Related Articles
SCE moves on more renewable power
CPUC approves first phase of renewables transmission link



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.