The US Nuclear Regulatory Commission (NRC) has issued the Tennessee Valley Authority (TVA) a construction permit for a 300 MW BWRX-300 small modular reactor (SMR) at the Clinch River site near Oak Ridge, Tennessee. The approval makes TVA the first US utility authorised to build GE Vernova Hitachi Nuclear Energy’s (GVH) BWRX-300 design, marking a step towards commercial deployment of the reactor in the United States.

TVA submitted its construction permit application in April 2025, building on an existing early site permit for Clinch River. The NRC’s decision is the second construction permit issued for an advanced reactor in the US, according to TVA. No construction start date has been announced.

TVA said the permit was issued ahead of schedule following the regulator’s review. The utility is continuing negotiations with industry partners on cost-sharing arrangements, saying it wants to ensure that customers do not bear the full financial risk of first-of-a-kind technology.

“This construction permit is more than a regulatory achievement – it’s foundational for America’s nuclear future,” said Mike Skaggs, TVA’s interim president and chief executive.

GVH said the approval could help establish a repeatable licensing route for further BWRX-300 projects. The reactor uses a simplified boiling water reactor design and draws on established operating experience, with the aim of reducing construction complexity.

“Fleet deployment is essential to scaling nuclear energy in the United States,” said Jason Cooper, chief executive of GVH. “A standard design, combined with a predictable and efficient regulatory environment, allows us to apply common technology, licensing experience, supply chain capabilities and lessons learned from one project to the next.”

The decision follows progress on the same design in Canada. Ontario Power Generation received a construction licence for the first BWRX-300 at its Darlington site in April 2025, and construction is under way. In September 2026, US developer Blue Energy submitted the first part of a construction permit application for a planned BWRX-300 in Texas.

Clinch River is located near the US Department of Energy’s Oak Ridge National Laboratory, within an established nuclear research and industrial centre. TVA and GVH see the project as a potential foundation for deploying additional standardised SMRs.