Fugro has been awarded a contract by German transmission system operator 50Hertz to survey, identify and support the clearance of unexploded ordnance (UXO) along the routes of two planned offshore grid connections in the German North Sea.
The work covers the LanWin3 and LanWin6 projects, each designed to transmit up to 2 GW of offshore wind power. Together, the connections will provide up to 4 GW of transmission capacity, linking offshore wind generation to Germany’s electricity network. The projects form part of the wider expansion of 2 GW high-voltage direct-current (HVDC) offshore connections in the North Sea.
Fugro will begin UXO surveys in the second quarter of 2027, covering corridors 200 m wide along the proposed cable routes. The surveys will use two of the company’s Geowing fixed magnetic gradiometer systems, each equipped with ten magnetic sensors to detect potential ordnance and other objects on or beneath the seabed.
Survey data will be used to map potential targets and compile a master target list for further investigation. Follow-up inspection and identification work is scheduled for 2028, using remotely operated vehicles and specialist detection equipment to examine selected targets and remove debris where necessary.
Fugro will also support the safe removal and disposal of confirmed UXO in accordance with applicable regulatory requirements, helping prepare the cable corridors for high-voltage direct current (HVDC) cable installation.
Ronny Bøhn, Fugro’s director of marine geophysics for Europe and Africa, said the survey would help establish a clearer picture of seabed hazards and give 50Hertz greater certainty when planning subsequent work.
The contract forms part of the preparatory work needed to develop Germany’s offshore wind transmission infrastructure. Identifying potential explosive hazards before cable installation is intended to reduce safety risks and help manage construction planning.