Olkiluoto NPP achieves first criticality

4 January 2022


Olkiluoto 3 nuclear plant in Finland (Photo: TVO)The EPR reactor installed at unit 3 of the Olkiluoto nuclear power plant in Finland achieved first criticality on 21 December, power utility Teollisuuden Voima Oyj (TVO) announced.

TVO said a new nuclear power plant was last commissioned in Finland more than four decades ago. OL3 will generate about 14% of Finland's electricity after the start of regular electricity generation.

“This moment will be remembered forever as a sign of the hard work to put our new plant unit into operation. It speaks of the strong professionalism in the nuclear industry and the desire to make Finland's largest climate work a reality,” said Marjo Mustonen, TVO Production Director. OL3 project manager Jouni Silvennoinen said OL3 will be connected to the national electricity grid in January 2022.

After start-up, the power level will be increased step by step with commissioning tests performed at each power level. Electricity production will start at a capacity of 30%, or about 500MWe, at the end of January 2022. OL3's regular electricity production will begin in June 2022.  

The Areva-Siemens consortium is constructing the OL3 plant under a fixed-price turnkey contract. They have joint liability for the contractual obligations until the end of the guarantee period of the unit. Construction of Olkiluoto 3 began in 2005 and completion of the reactor was originally scheduled for 2009. However, the project faced a series of delays and setbacks. The project to build OL3 is some ten years behind schedule and significantly over budget. STUK project manager Essi Vanhanen   said construction of the plant has been 'a learning place for everyone involved'.

“We commend the TVO teams for this significant milestone and we thank the Framatome and Areva project teams that persevered to reach it. This milestone paves the way for safe, reliable, low-carbon electricity generation to the residents of Finland,” said Bernard Fontana, CEO of Framatome. “From the fuel manufactured in our plants to the long-term operational and outage services that Framatome will supply to OL3 in the future, we are honored to support this unit in reaching its full potential.”


Olkiluoto 3 nuclear plant in Finland (Photo: TVO)



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.