Statkraft Energi AS has contracted with Voith to modernise the Sima hydropower plant, a critical asset in Norway’s renewable energy infrastructure. Commissioned in 1980, the country’s second-largest hydropower plant will undergo extensive modernisation of its electrical power and automation systems. The primary goals are to extend the operational lifespan of the station, secure high plant availability for the long term, and reduce the risk of failures and unscheduled downtime in the future.
To avoid downtime, Voith will carry out the work of modernisation while the plant remains in operation. By integrating new components into existing infrastructure in a carefully managed process, Voith expects to secure the plant’s reliable operation throughout the transition period. This step-by-step approach to replacing the plant’s entire control and electrical systems is key to maintaining plant availability and minimising the risk of unscheduled shutdowns during the extensive upgrades.
The Sima hydropower plant features two waterways and four generating units amounting to a total installed capacity of 1120 MW; it generates roughly 3100 GWh of renewable energy annually. Under the contract, Voith will take full scope responsibility for the modernisation of the existing control system.
Statkraft is Norway’s and Europe’s largest producer of renewable energy. Its hydropower plants generate roughly one-third of the country’s power output.
Full responsibility
As part of the refurbishment, Voith will supply electrical and balance-of-plant equipment, including software that is developed and maintained by in-house specialists. The plant will be equipped with new automation systems, electrical protection systems, new AC/DC systems and various medium voltage components including cabling.
“We have partnered with Statkraft for more than twenty years, which gives us in-depth knowledge of their requirements and a clear perspective on the complexities involved in the modernisation of the Sima plant,” said Oeyvind Holm, head of Sales Norway at Voith Hydro. “By taking full responsibility for this project, we are able to streamline processes, minimise risks, and ensure a smooth and rewarding experience for everyone involved.”
“The Sima hydropower plant …. has been generating electricity since 1980,” said Kristin Lindvik, power plant manager at Statkraft. “Our goal is to extend its lifetime in the most sustainable and efficient manner possible. It is crucial that modernising such a critical plant is performed safely and efficiently with minimal disruption to our operations and production of renewable power.”