Vattenfall has completed installation of all 68 foundations for its 980 MW Nordlicht I offshore wind farm in the German North Sea, finishing the work ahead of schedule.
The final monopile was installed at the end of September, with all transition pieces also in place. Each foundation comprises a monopile secured in the seabed and a transition piece that will connect it to the turbine tower.
EEW Special Pipe Constructions and CS WIND Offshore manufactured the foundations, while DEME transported and installed the monopiles and transition pieces.
Work is continuing across the project’s supply chain. Cable production by TKF and tower manufacturing by Vestas are under way, with the first tower sections delivered to Esbjerg. Production of blades and nacelles is expected to start in the coming months. Preparations for the second project in the cluster, Nordlicht II, are also progressing.

Nordlicht I is located approximately 85 km north of Borkum. First power from the Nordlicht cluster is expected in 2028, with full commissioning planned for 2029.
The cluster will combine Nordlicht I, with a planned capacity of around 980 MW, and Nordlicht II, at approximately 630 MW, giving a total capacity of more than 1.6 GW. Vattenfall expects the completed cluster to generate around 6 TWh of electricity annually.
The company said low-emission steel is being used in parts of the turbine towers and that environmental monitoring, including systems tracking bird and marine mammal activity, is taking place during construction.