The EIA process is required before for a possible application for a decision in principle on the Loviisa 3 nuclear power unit. In the first phase of the process, the EIA programme will be compiled for submission to the Ministry of Trade and Industry by the end of June 2007. Once the Ministry’s statement on the programme has been received, work on the actual EIA report can begin. Fortum will submit its Loviisa EIA report to the Ministry of Trade and Industry in June 2008.