Viridor and Tees Valley Energy Recovery Limited (TVERL) have reached financial close on a £2bn, 29-year contract to develop and operate a residual waste-to-energy facility at Teesworks in Redcar, north-east England.

The Tees Valley Energy Recovery Facility (TVERF) is scheduled to enter operation in 2030 and will process approximately 450,000 tonnes of residual waste annually. Its two-line design will enable it to generate up to 49.9 MW of baseload electricity for the local grid.

Construction is due to begin later in 2026, with Kanadevia Inova appointed as the engineering, procurement and construction (EPC) contractor. The facility will be built on disused industrial land at Teesworks.

The project is being delivered through a public-private partnership involving seven local authorities: Darlington, Durham, Hartlepool, Middlesbrough, Newcastle, Redcar and Cleveland, and Stockton. The councils are represented on the board of TVERL, the special-purpose company that has contracted Viridor to design, build, finance and operate the facility.

The plant is intended to provide long-term treatment capacity for residual waste remaining after recycling and reuse. The partners said the development would also support employment and economic activity in the region.

“Today we are celebrating the fact that Tees Valley Energy Recovery Facility has reached financial close and will join the growing Viridor EfW fleet,” said Richard Belfield, Viridor’s group development director.

Kanadevia Inova executive vice-president of business development Fabio Dinale said the company had received notice to proceed and was preparing to start full construction works.

The project will become the 13th facility in Viridor’s energy-from-waste portfolio across England, Scotland and Wales, according to the company.